Appoint expert engineer to ascertain exact degree of overbridge in Bhopal: MP HC

Published on: Aug 27, 2025 03:04 PM IST

ONn June 28, the Madhya Pradesh government suspended seven engineers including two chief engineers of the Public Works Department for the `faulty design’

The Madhya Pradesh High Court division bench on Tuesday ordered to appoint an expert engineer to ascertain the exact degree of the railway overbridge in Aishbagh area of Bhopal.

The court also ordered no further coercive action shall be taken against the company till the next date of hearing. (ANI photo)

The infamous bridge faced brickbats for its 90 degree design. The HC also asked to compare the design of Public Works Department (PWD) officers and work done by the architect company.

High court chief justice Sanjeev Sachdev and justice Vinay Saraf’s issued orders not to take any strict action against the private contractor architect company after the company filed a petition with design of General Arrangement Drawing (GAD) of Public Works Department and said the degree of bridge is 119 degree.

Company advocate Praveen Dubey contended that the construction has been made strictly in-accordance with the drawing and the action has already been taken against some officers of the department for faulty drawing.

“The company shouldn’t be held liable for a design fault as the construction is strictly in accordance with the General Arrangement Drawing,” he said.

“The expenses in the inspection including fees of the engineer to be borne by the company subject to right of recovery from the state government depending on the report. Copy of this order along with the copy of the General Arrangement Drawing be forwarded to the Director, Maulana Azad National Institute of Technology, Bhopal for necessary compliance,” said the court.

The court also ordered no further coercive action shall be taken against the company till the next date of hearing.

The company got the contract for construction of a flyover in Aishbagh area in 2021-22. The flyover was to be constructed in 18 months. The GAD of the bridge was issued by the government. After this, the GAD was amended in the year 2023 and 2024 and the bridge was constructed accordingly.

After the matter came to light on social media about the fault in the bridge due to the 90 degree turn, the government constituted a five-member committee for investigation.

The investigation committee found that there was a lack of coordination between the state government and the railway department. Apart from this, the pillars of the bridge have not been installed at the prescribed distance.

On the basis of the report of the investigation committee, the company has been blacklisted by the government.

Seven engineers of the Public Works Department including two chief engineers have been suspended over the serious negligence.

A departmental inquiry is being conducted against a retired superintendent. Two companies including the private contractor have been blacklisted.

(With inputs from Monika Pandey)

 