Ludhiana: 70% posts vacant, PSPCL officials fail to ensure maintenance work

ByRishika Kriti, Ludhiana
Published on: Sep 24, 2025 05:24 AM IST

The manpower crunch has left office complexes, and other infrastructure in a dilapidated state, with leaking roofs, crumbling walls and broken facilities becoming a common sight across the district

With nearly 70% of the posts lying vacant in the civil wing of Punjab State Power Corporation Limited (PSPCL), the corporation is struggling to maintain its offices, residential quarters and guest houses across Ludhiana district. The severe manpower crunch has left office complexes, and other infrastructure in a dilapidated state, with leaking roofs, crumbling walls and broken facilities becoming a common sight across the district.

The false ceiling of the office in Focal Point area had recently collapsed during heavy rainfall. (HT File Photo)

According to official data, out of 26 sanctioned posts in the civil department, only eight are currently filled. Among 17 technical posts, just four are occupied including one junior engineer, two subdivisional officers and one executive engineer.

Reportedly, the civil wing of the PSPCL central zone is responsible to look after over 19 division offices, staff quarters and guest houses across the district for which the wing has surprisingly only four technical staff.

Dilapidated offices

The crisis came into sharp focus earlier this month when the false ceiling at the Suvidha Centre in Focal Point collapsed during heavy rainfall on September 3. The damage forced the centre to suspend public dealings. Services such as applying for new connections, bill payments, security deposits and replacement of faulty meters were halted.

Financial crunch

Highlighting the crisis, PSPCL officials noted that the corporation’s spending is largely diverted towards infrastructure upgrades and subsidy commitments, leaving little for building upkeep. “The free electricity subsidy of 300 units has further drained resources. Whatever little budget is available gets spent on priority infrastructure, while maintenance of offices and colonies is pushed to the backseat,” an official explained.

When contacted, Punnardeep Singh Brar, chief engineer (protection and maintenance wing), said,” The civil wing is facing staff crunch but we are undertaking the essential repairs as per needs. The conditions of buildings have decayed after rainfall where we have addressed safety concerns.”

Deferring the financial constraints claims, Brar noted that the civil wing is not facing any budget issues by stating,” We receive annual funds which are used to carry out necessary maintenance.”

 