Next Story

NGT slaps 25k fine on pvt firm for response delay in EDC case

Published on: Aug 17, 2025 06:28 AM IST

NGT, Western Zone Bench, Pune, imposed ₹25,000 fine on private rubber manufacturing company in Talegaon Dabhade after it failed to submit reply on Environmental Damage Compensation (EDC) case

Pune: The National Green Tribunal (NGT), Western Zone Bench, Pune, has imposed a fine of 25,000 on private rubber manufacturing company located in Talegaon Dabhade after it failed to submit its reply in a matter concerning Environmental Damage Compensation (EDC).

NGT, Western Zone Bench, Pune, imposed 25,000 fine on private rubber manufacturing company in Talegaon Dabhade after it failed to submit reply on Environmental Damage Compensation (EDC) case. (HT FILE)

The order was passed on August 12 after the tribunal noted repeated delays despite sufficient time being granted.

The Maharashtra Pollution Control Board (MPCB) had, in April this year, proposed a penalty of 1.44 crore against the company. The firm is engaged in the development and production of rubber and plastic components used in various applications. Following MPCB’s proposal, the company was directed to file its response within a week. However, even after four months, no reply was filed, nor was any justification offered.

Expressing displeasure, the bench, comprising Justice Dinesh Kumar Singh, judicial member, and Vijay Kulkarni, expert member, imposed the fine and warned that further delay would not be condoned.

The tribunal has directed the company to deposit the penalty amount with the NGT Bar Association, Western Zone Bench, Pune, within eight days.

 